During the change from Phase II to Phase III in EU ETS it was necessary for incumbents and new entrants to submit an application for a Phase III permit to align with the 2012 Monitoring and Reporting Regulations.

IAMC Ltd were contracted to provide training to EA staff, NRW staff and other sub-contractors on the assessment of these permit applications. A two training course was written and presented by Alan Lloyd at the EA offices in Warrington in September 2012.

Alan subsequently provided project management support and technical assistance to the repermitting team throughout the process until all 700 permits were completed in December 2012.

The Environment Agency of England successfully issued the Phase III permits for all of its operators ahead of many of the other European countries.